The fourth phase of the project life cycle involves ____ the project.

Respuesta :

MrsTriplet MrsTriplet
  • 11-03-2018
In project management there are four phases of the project life cycle. 
1) Initiation
2) Planning
3) Performing
4) Closing

The closing of the project involves finalizing all data collected, documenting and evaluating the project. This step is major in the phase because it is a reflection of the entire project and is usually turned into a superior.
Answer Link

Otras preguntas

is 24x + 12 and 24 + 12x equivalent
0.9+{[3.25−(6 9/16 −0.025y)·0.6]÷0.75}÷6 2/3 =1.2 solve for y PLZ SOLVE DO NOT PUT INCORRECT ANSWERS I BEG PLEAS AND THANK YOU
According to the old woman, what brings the most happiness to marriage
Pls someone anyone help I need it ASAP!!!
A gas that has a volume of 28.0 liters, a temperature of 45.0 °C, and anunknown pressure has its volume increased to 34.0 liters and itstemperature decreased to
Ashley and Kristin are selling wrapping paper for a school fundraiser. Customers can buy rolls of plain wrapping paper and rolls of shiny wrapping paper. Ashl
In a company, 60% of workers are men. If 1,380 women work for the company, how many workers are there in all? Show two different ways you can solve this problem
why was west Africa important to the Europeans
What is the (?,?) coordinates? My teacher said it was h-m as the x coordinate, but im saying it is h+m. Can anyone help? (13 points)
Please answer questions 6 and 7 please