If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

The length of a diagonal of a cube with edge length 25cm
the cafeteria has 45 square  tables that can be pushed together to form one long table for the lacrosse team's banquet. Each square table can seat one person on
How many atoms are in 0.750 moles of zinc?
Find all powers of 4 in range 4 through 1,000
What are the 3 features of a typical seigneurie
Why was is difficult for the Arab people to form one nation?
Natalie earns $2.50 for each cd she sells and $3.50 for each dvd she sells.  Natalie sold 45 dvds last year.  She earned a total of $780 last year selling cds a
What are the 3 features of a typical seigneurie
How did scientists discover the common structure of cells?
If Walt can paint 25 feet of fence in an hour, and Joe can paint 35 feet in an hour, how many minutes will it take them to paint a 150-foot fence, if they work