Consider the following project network and activity times (in weeks): Activity A B C D E F G H Time 5 3 7 6 7 3 10 8 How much time will be needed to complete this project

Respuesta :

codiepienagoya codiepienagoya
  • 04-07-2021

Answer:

Please find the attached file of the complete question:

Explanation:

Please find the attached file of the solution:

Critical Path:  ACH

Duration: 21

Because C is on the Critical Path, it cannot be postponed without causing the project to be delayed.

E is not on the critical path, thus it may also be delayed by two weeks without causing the project to be delayed.

[tex]D : ES : 6, EF : 10, LS : 7, LF : 11[/tex]

Ver imagen codiepienagoya
Ver imagen codiepienagoya
Answer Link

Otras preguntas

what was Margaret Brent accomplishments
can someone help me with number 25
How is the graph of y=-8x^2-2 diffrent from the graph of y=-8x^2
find the derivative of ((t^4-6)^3)*((t^3+6)^4)
Questions 1. Calculate the molar mass of an element. 2. Calculate the molar mass of a compound. 3. How do you determine the number of protons, electrons and neu
Trent and Chris are musicians, and they recently played a concert for 20,000 fans. The rectangular venue measured 87 yards by 57 yards. What was the approximate
How long does interphase last?
name 1 element in the periodic table that sounds like a name
The pressure within a 5.75L balloon is 2.00 atm. If the volume of the balloon increases to 8.45L, what will the final pressure within the balloon be if the temp
How many counting numbers are between 30 and 65, not including 30 and 65?