it takes 8 labours 6days to complete a certain job.how many labours would complete the job in 15 days.​

Respuesta :

lakminirsenarath lakminirsenarath
  • 30-07-2021

Answer:

Step-by-step explanation:

Required man days to complete the job = 8 * 6

                                                                   = 48 Man Days

Required labors to complete the job by 15 days = 48/15

                                                                               = 3.2

It means, it is required 4 labors can complete the certain work by 15 days

Answer Link

Otras preguntas

1. paid a proper tribute
help me out with some questions!!!!
Explain the difference between a calorie and a kilocalorie​
Which of the following describes the ocean floors sudden sharp decline in elevation? a. Continental Rise b. Continental Shelf c. Continental Drop d. Continental
Given the following information about a CMO: - $1 million of mortgage pool principal assigned to the floater class. $15 million assigned to the inverse floater
Angelica Baggins had considered not attending the party, but curiosity got the better of her. When she arrived, Bilbo himself presented her with a gift, an intr
I need help thanks hullo
We elect a President for how many years? 8 2 4 6
Can you guys answer this pleaseee
Hey can you please help me? Thanks have a nice day.